| Project Name | KitchenSync |
| Team Members and Email Addresses | David Tran - dtran2021@my.fit.edu |
| Tyler Son - tson2022@my.fit.edu | |
| Chris Nederhoed - cnederhoed2020@my.fit.edu | |
| Faculty Advisor | Fitzroy Nembhard |
| Plan (Sep 4) | Plan, Presentation |
| Milestone 1 (Sep 30) | Requirement, Design, Test, Presentation, Progress Evaluation |
| Milestone 2 (Oct 28) | Presentation, Progress Evaluation |
| Milestone 3 (Nov 25) | Presentation, Progress Evaluation |
| Plan (Jan 27) | Plan, Presentation |
| Milestone 4 (Feb 24) | Presentation, Progress Evaluation |
| Milestone 5 (Mar 26) | Poster, e-book page, Presentation, Progress Evaluation |
| Milestone 6 (Apr 21) | User and/or Developer Manual, Demo Video, Presentation, Progress Evaluation |